Eight 132/33 kV Mobile Substations in Madinah, Taif, Jeddah and Tabuk
Al Sharhan Energy Company has successfully completed the installation, testing and commissioning of eight 132/33 kV HV Mobile Substations manufactured by CEEI and TBEA for Saudi Energy – National Grid.
Al Sharhan Energy's engineering and field teams took every unit from installation to energization, to the highest standards of safety and quality and on a tight schedule.
Project sites
City | Mobile substations | Manufacturer |
|---|---|---|
Madinah | Madinah East · MODON | CEEI |
Taif | Mafrq Sudayrah · Bahitah · Jalil | CEEI |
Jeddah | HHR1 | TBEA |
Tabuk | Sub2 · Sub5 | TBEA |
15 HV mobile substations in two months
These 8 units are part of 15 HV mobile substations that Al Sharhan Energy energized within two months.
Civil works · Installation · Testing · Commissioning · Energization